Progress Report August 25, 2022

Written on
August 25, 2022

Phases II, III and IV

Read More

Progress Report July 2022

Written on
July 2, 2022


Building:

- Dry-wall 100% Complete!

- Interior Painting in Process.

- Main Hangar Floor and Bathrooms have been epoxy coated.

- Restrooms and Family Restroom / Shower Fixtures to be installed next week!

- Lobby / Conference Room Flooring to be installed shortly. 

Funding:  A great big “Thank You” to everyone who has participated with the funding of the International Stearman Community Center! Phase II – first floor interior buildout / restrooms / conference room / lobby is well underway, but we still need your help! Funding will be needed to complete Phase III, second floor interior walls/finishings, flooring, elevator, and furniture! 

Read More

Progress Report April 2022

Written on
April 1, 2022


Building: - All Interior Steel Construction 100% Completed! - Dry-wall approximately 75% Complete - Restrooms and Family Restroom / Shower approximately 75% Complete 

Funding: A great big “Thank You” to everyone who has participated with the funding of the International Stearman Community Center! Phase II – interior build-out is well underway, but we still need your help! Funding will be needed to complete the flooring, interior wall finishings, and furniture! 

Read More

Progress Report January 2022

Written on
January 1, 2022


Building: - Approximately 50 % of the 1st Floor (restrooms / utility room) steel is framed. - In-Floor heat has been installed and fully operational. - Interior layout adjustments have been made and final plans have been approved for Phase II! - Permit has been issued – the interior build-out for the 1st Floor and 2nd Floor to begin in February. 

Funding: A great big “Thank You” to everyone who has participated with the funding of the International Stearman Community Center! Over $688,000 has been raised to date and everything up to date has been fully paid! The estimated cost to finish Phase II - the interior on both floors (restrooms / lobby / conference room / library) is $500,000 so we are well underway, but we are currently about $200,000 short of our goal. 

Read More

Progress Report October 2021

Written on
October 1, 2021


Building: - Temporary Occupancy Permit approved for use during the National Stearman Fly-In! - Daily Pilot Briefing / Seminars / “Remembering 9/11/2001” conducted in new facility! - Approximately 50 % of the 1st Floor (restrooms / utility room) steel is framed. - Interior layout adjustments have been made and final plans are being prepared for approval. - Phase II – the interior build-out to begin on first floor this Fall. 

Funding: A great big “Thank You” to everyone who has participated with the funding of the International Stearman Community Center! During the National Stearman Fly-In, a group of anonymous individuals challenged a MATCH (dollar for dollar) for funds raised during the Stearman Fly-In. Over $125,000 raised to date – Thank You! The estimated cost to finish the interior on both floors (restrooms / lobby / conference room / library) is $500,000 so we are well underway, but we still need your help! 

Read More