Progress Report January 2022

Written on
January 1, 2022


Building: - Approximately 50 % of the 1st Floor (restrooms / utility room) steel is framed. - In-Floor heat has been installed and fully operational. - Interior layout adjustments have been made and final plans have been approved for Phase II! - Permit has been issued – the interior build-out for the 1st Floor and 2nd Floor to begin in February. 

Funding: A great big “Thank You” to everyone who has participated with the funding of the International Stearman Community Center! Over $688,000 has been raised to date and everything up to date has been fully paid! The estimated cost to finish Phase II - the interior on both floors (restrooms / lobby / conference room / library) is $500,000 so we are well underway, but we are currently about $200,000 short of our goal. 

Read More

Progress Report October 2021

Written on
October 1, 2021


Building: - Temporary Occupancy Permit approved for use during the National Stearman Fly-In! - Daily Pilot Briefing / Seminars / “Remembering 9/11/2001” conducted in new facility! - Approximately 50 % of the 1st Floor (restrooms / utility room) steel is framed. - Interior layout adjustments have been made and final plans are being prepared for approval. - Phase II – the interior build-out to begin on first floor this Fall. 

Funding: A great big “Thank You” to everyone who has participated with the funding of the International Stearman Community Center! During the National Stearman Fly-In, a group of anonymous individuals challenged a MATCH (dollar for dollar) for funds raised during the Stearman Fly-In. Over $125,000 raised to date – Thank You! The estimated cost to finish the interior on both floors (restrooms / lobby / conference room / library) is $500,000 so we are well underway, but we still need your help! 

Read More

Progress Report September 2021

Written on
September 1, 2021

Phase I Site prep / purchase and erection of the hangar shell $750,000 - Completed as of September 2021 

Phase II Completion of the Full Interior (2 Stories) $500,000 - Approximately 15% Complete - Additional funding is needed to complete the interior 

Phase III Endowment $500,000 

Read More

Progress Report July 2021

Written on
July 1, 2021

Construction Update!

Read More

Progress Report May 2021

Written on
May 19, 2021

What's new as of May 2021

Read More